FOUR YEARS OF MINUTES: A SLOW-MOTION CHAIN REACTION

Thirty-nine sets of Regents minutes. Two land votes. Number of times anyone wrote down what the land was for: zero.

ANN ARBOR — A chain reaction is supposed to be fast. The one inside the University of Michigan Board of Regents has taken about four years, and most of it happened somewhere other than the minutes.

YpsiDataCenter.org read 39 sets of Regents minutes covering February 2022 through September 2026.1,5 For roughly the first thirty meetings, the project does not appear at all.1

It was busy offstage. In March 2023 the university signed a restricted nondisclosure agreement for a computing facility supporting the "Advanced Simulation & Computing Program and Weapons Physics Directorate."2 In October 2023 the state's economic development chief wrote to then-President Santa Ono committing up to $400 million in state support.3 In May 2024 came confidentiality agreements with the Michigan Economic Development Corporation and Willow Run Arsenal of Democracy Landholdings.1 The minutes mention none of it.1

The reaction finally became visible on October 17, 2024, when the Regents unanimously approved buying 10221 Textile Road for $1,500,000 (along with a parcel on Rawsonville Road for $1,155,000), "subject to the university satisfying itself with the environmental condition of the site."1 Purpose stated: none.1

On December 5, 2024, President Ono told the Regents about an "Artificial Intelligence (AI) research facility" with Los Alamos. Five days later, the state approved $100 million.1

On June 12, 2025, the Regents approved buying 10455 and 10635 Textile Road at $65,000 per developable acre. The minutes again record no purpose. The action request behind the vote called it "a future computing center."1

In February 2026, President Grasso described a "world-class supercomputing research center."1 Over the whole stretch, the minutes show four public commenters raising the project. One, the township supervisor, appears as a "community member."1

The university's own capital project guidelines require two separate Board approvals for new construction of $3 million or more.4 The fallout, in other words, is still on its way.

The Receipts

Every factual statement above links to one of these. Quotation marks mean verbatim.

  1. YpsiDataCenter.org, "Four Years of Regents Minutes"
  2. Restricted NDA RSNDA-23-0076, March 2023 (PDF)
  3. MEDC letter to President Santa Ono, Oct. 27, 2023 (PDF)
  4. University of Michigan Capital Project Guidelines (PDF)
  5. University of Michigan Board of Regents, meeting minutes
SatireYpsi Data Center Daily is satire. The framing is a joke; the facts are not. Found an error? See corrections.
Federal Funding

SHOW ME THE FUNDS: LANL'S COMMITMENT STILL SUB-CRITICAL

Lab's $300 million contribution remains in a stable state of not existing, university confirms in writing.

Physics

TEXTILE ROAD: WHERE THE FABRIC OF THE COMMUNITY GETS SPLIT LIKE AN ATOM

The "academic research center" undergoes fission into two very unequal parts. Guess which one is classified.

Nuclear Linguistics

THE HALF-LIFE OF A PROMISE

Researchers measure how long it takes a "Weapons Physics Directorate" project to decay into "An academic research center." Result: about three and a half years.